Burlington data centre beside the QEW: a noise and vibration study for Site Plan

The site

A data centre proposed on South Service Road in Burlington, right beside the QEW/Highway 403 corridor. The application was at Site Plan with the City of Burlington, and the client needed a noise and vibration control study.


Data centres are an odd mix acoustically. They're loud on the outside, because of the cooling and backup-power equipment. They also have occupied spaces inside that face a highway. And the equipment in the data halls can be fussy about vibration. This site had all three issues.


What we looked at

Noise coming in. The site is directly exposed to highway traffic, so we assessed road noise at the building's occupied spaces.


Noise going out. We modelled the chillers, transformers and generator testing, along with existing commercial equipment nearby, at the surrounding receptors. At Site Plan the equipment selections weren't final, so the model was built on assumed sound levels for each unit.


Vibration. Heavy highway traffic puts vibration into the ground. We used vibration measurements taken at the site earlier and compared them with a vibration criterion commonly used for sensitive equipment (VC-A), to judge whether the site suits the facility.


What we recommended

  • Upgraded glazing on the north facade, the side facing the highway, subject to a final architectural review.
  • Equipment quantities, locations and manufacturer sound data confirmed before building permit. A chiller swap or an extra generator late in design can change the results, so the assumptions need checking against what's actually ordered.
  • The data-hall equipment suppliers to confirm that the vibration criterion we adopted suits their equipment. They know their tolerances better than anyone, and we'd rather they sign off on that than assume.


If you're planning an industrial, commercial or mission-critical building near a highway or homes, see our industrial and environmental noise assessments, or our page on noise studies for Site Plan. You can also call us at (905) 707-5800, or send your drawings through our contact page.


Photo: Mathew Campbell, CC BY 2.5, via Wikimedia Commons

Aerial view of new townhouses beside vacant development land in Brampton, Ontario
By Omar Rahal • November 25, 2026
Feasibility or detailed noise study? When each one is needed for an Ontario OPA, rezoning, draft plan or Site Plan application, and what each covers.
Residential condominium towers on Yonge Street in Richmond Hill, Ontario
By Omar Rahal • November 23, 2026
Detailed noise study for residential towers on Yonge Street in Richmond Hill, for rezoning and an OPA. Road traffic plus the building's own equipment.